Site Visit Report

SVR-0087 · Riverside Block B · 14 Oct 2026 · Sample data

NL

Summary

Weekly coordination visit covering the level 3 slab, the stair core and the east façade scaffold. Weather was dry and overcast, 19 °C. Works on site: formwork for level 4, rebar fixing at grid C–D, and façade anchors on the east elevation.

Three observations were raised. One needs action before the level 4 pour; two are for monitoring. Photos and locations are attached to each observation in the field app.

Observations

IDLocationFindingAction
10-01L3 slab edge, C/4Rebar cover below specFix before pour
10-02Stair core, east wallHairline crack above landingMonitor
10-03L3 column C3Honeycombing at baseRepair method to follow
10-04East scaffold, lift 6Missing toe boardClosed on site

Next steps

Contractor to submit the cover correction method by Thursday. Engineer to review the column repair proposal before the next visit. Next coordination visit is scheduled for 21 Oct 2026.

Attendance

Sign-off

Inspector